PEDA wants bids by 29 October 2026 for 50 MW of RESCO solar on Punjab government buildings, on rooftops or the ground, where a developer owns the plants and the buildings buy their power for 25 years: about half the capacity on all of Punjab's homes under the national scheme. Few small installers may bid, but the winners could need local crews, stock and service long after the bid: in J&K, where a 152 MW plan of the same kind has work orders out, officials are now pressing for meters and power purchase agreements.

What happenedPEDA/2026-27/18: 50 MW RESCO solar on govt buildings, bids by 29 Oct

PEDA, the Punjab Energy Development Agency, published tender PEDA/2026-27/18 on the state's e-procurement portal on 7 October 2026, as Tender ID 2026_PEDA_176894_1. The portal's title calls it a tentative 50 MWp of grid-connected rooftop solar under the RESCO model, “at various locations in the State of Punjab”, with a payment security mechanism. SolarQuarter and Mercom reported it on 8 October as rooftop and ground-mounted plants with net metering or net billing, and Saur Energy reported on 9 October that the sites are government buildings. We have now read the tender document, downloaded from the portal. It covers government buildings in Punjab: state and local government offices, other government institutions such as schools and health centres, and buildings of government-owned bodies. Its notice says rooftop or ground-mounted plants “anywhere in State of Punjab”, and its scope says the same for government buildings, though its cover title says rooftop only. Bidders must find the buildings themselves, and a department's no objection certificate can bring in other government buildings. The draft power purchase agreement listed in its contents is not attached to the file we downloaded.

RESCO stands for renewable energy service company: the developer pays to put up the plant at the site, and the site buys its power at a fixed rate for a set period, usually 25 years, as the Delhi government's solar portal describes it. In this tender, the developer owns the plants and runs them for 25 years: each power purchase agreement ends 25 years after the date the plant is due to start supplying power, which the tender sets at six months after the agreement is signed. The developer then hands the plant over to the department without charge, still giving at least 80 per cent of its output. Capacity goes to the lowest rate per unit quoted for those 25 years, with one price for all bidders in each size band: other bidders must match the lowest rate to win capacity, and matching does not guarantee it. Once its payment security fund is set up, PEDA pays developers centrally from a fund worth two months of bills, within seven days of a valid invoice, and the developer gives a 1 per cent rebate for that.

PEDA set a pre-bid meeting for 11:30 am on 15 October 2026, at its Chandigarh head office and online. Bids are due by 5 pm on 29 October, and the techno-commercial bids are opened at 10:30 am on 3 November. Bidders pay earnest money of Rs 10 lakh a MW, and a winner gives a performance bank guarantee of Rs 20 lakh a MW within 15 days of its allocation letter, the tender document says. SolarQuarter had reported Rs 10 lakh for the guarantee. The portal lists one earnest money figure, Rs 5 crore (Rs 10 lakh a MW across 50 MW), and says an exemption is allowed. The tender's checklist accepts a micro or small enterprise (MSE) certificate instead of earnest money, without saying which certificate, and elsewhere it says bids without earnest money are rejected. The smallest bid PEDA accepts is 1 MW, and a winner pays PEDA a one-time service charge of Rs 1,350 a kW plus 18 per cent GST within 30 days of each project's work order.

To bid, a firm needs two years in the solar business, and grid-connected plants it supplied, installed and commissioned itself since 1 September 2019 that add up to at least 40 per cent of the capacity it quotes. The tender's experience form counts only commissioning reports verified by a state nodal agency or a government agency, though its eligibility clause also accepts lists verified by the client, including a private one; work orders do not count. The firm's average audited turnover over three of the last four financial years must reach Rs 80 lakh for each MW it quotes. Consortiums are not allowed: the bidder must meet these tests on its own.

In June, PEDA asked for bids on 10 MW at government building sites in Punjab and Chandigarh, Mercom reported. In that tender, PEDA picks the firms and their rates, and government departments pay for the plants; it asked for cells and panels from ALMM List-I and List-II, India's approved lists of panel and cell makers. The October tender is five times the size, and under RESCO the developer pays.

In Jammu and Kashmir, a review held by the UT's Chief Secretary on 7 October heard that JAKEDA, the UT's energy development agency, has proposed solar on 8,000 government buildings under RESCO, 152 MW in all, with work orders placed for 5,185 of them. NHPC has proposed another 1,500 government buildings, 23 MW, Kashmir Observer and Kashmir Images reported. Kashmir Observer said the Chief Secretary asked JAKEDA to speed up RESCO work, noting that progress had “remained slow”. The same review heard that 8,850 government buildings, 95.64 MW, are already solarised under other programmes.

What our tracker showsPunjab and J&K home rooftop capacity, 14 Sep to 14 Oct 2026

Our tracker reads the national PM Surya Ghar portal every day. It counts home rooftops under the national scheme only: not government buildings, shops, factories, ground-mounted plants or homes that went solar outside the scheme.

Punjab: on the 14 October reading, 20,788 home rooftops with 95.05 MW. On the 14 September reading it was 19,410 rooftops and 87.99 MW, so in 30 days Punjab added 1,378 home rooftops and 7.06 MW. PEDA's 50 MW is about half (53 per cent) of all the capacity on Punjab's scheme homes, and about seven months of home rooftops at the pace of the last 30 days. At Punjab's average home system of about 4.6 kW, 50 MW is the size of about 11,000 home rooftops.

Jammu and Kashmir: 47,197 home rooftops with 169.07 MW on the 14 October reading, up from 43,885 and 157.10 MW on 14 September, so 3,312 rooftops and 11.98 MW in 30 days. JAKEDA's 152 MW plan is about nine-tenths of all J&K's scheme home capacity. With NHPC's 23 MW, the two plans come to 175 MW, a little more than all of J&K's scheme homes put together. Our 5 October reading, 46,135 rooftops and 165.25 MW, matches the review's 46,133 and 165.24 MW.

A tender is a plan, not a plant. None of PEDA's 50 MW is built, and the final size and sites depend on the bids and on which government buildings sign power purchase agreements, and PEDA may raise or cut the 50 MW. The J&K figures are proposals, with work orders for about two-thirds of JAKEDA's buildings.

Home rooftops under the national scheme, against the RESCO plans
Home rooftops under the national scheme, against the RESCO plans (MW) Punjab: scheme home rooftops, 14 Oct: 95.05 MW MW; Punjab: home rooftops added, 14 Sep to 14 Oct: 7.06 MW MW; Punjab: PEDA RESCO tender: 50 MW MW; J&K: scheme home rooftops, 14 Oct: 169.07 MW MW; J&K: home rooftops added, 14 Sep to 14 Oct: 11.98 MW MW; J&K: JAKEDA RESCO plan, government buildings: 152 MW MW; J&K: NHPC plan, government buildings: 23 MW MW. Punjab: scheme home rooftops, 14 Oct 95.05 MW Punjab: home rooftops added, 14 Sep to 14 Oct 7.06 MW Punjab: PEDA RESCO tender 50 MW J&K: scheme home rooftops, 14 Oct 169.07 MW J&K: home rooftops added, 14 Sep to 14 Oct 11.98 MW J&K: JAKEDA RESCO plan, government buildings 152 MW J&K: NHPC plan, government buildings 23 MW Home rooftops under the national scheme, against the RESCO plans (MW) Punjab: scheme home rooftops, 14 Oct: 95.05 MW MW; Punjab: home rooftops added, 14 Sep to 14 Oct: 7.06 MW MW; Punjab: PEDA RESCO tender: 50 MW MW; J&K: scheme home rooftops, 14 Oct: 169.07 MW MW; J&K: home rooftops added, 14 Sep to 14 Oct: 11.98 MW MW; J&K: JAKEDA RESCO plan, government buildings: 152 MW MW; J&K: NHPC plan, government buildings: 23 MW MW. Punjab: scheme home rooftops, 14 Oct 95.05 MW Punjab: home rooftops added, 14 Sep to 14 Oct 7.06 MW Punjab: PEDA RESCO tender 50 MW J&K: scheme home rooftops, 14 Oct 169.07 MW J&K: home rooftops added, 14 Sep to 14 Oct 11.98 MW J&K: JAKEDA RESCO plan, government buildings 152 MW J&K: NHPC plan, government buildings 23 MW

Darker bars: PEDA's tender and the two J&K plans, planned capacity, not built capacity. Home rooftop bars: Solentra's daily readings of the national PM Surya Ghar portal, 14 Sep and 14 Oct 2026, homes under the national scheme only. PEDA: tender PEDA/2026-27/18 on Punjab's e-procurement portal, read 14 Oct 2026, and the tender document, read 15 Oct 2026. J&K plans: Kashmir Observer, 7 Oct 2026.

See the numbers
Home rooftops under the national scheme, against the RESCO plans
ItemMW
Punjab: scheme home rooftops, 14 Oct95.05 MW
Punjab: home rooftops added, 14 Sep to 14 Oct7.06 MW
Punjab: PEDA RESCO tender50 MW
J&K: scheme home rooftops, 14 Oct169.07 MW
J&K: home rooftops added, 14 Sep to 14 Oct11.98 MW
J&K: JAKEDA RESCO plan, government buildings152 MW
J&K: NHPC plan, government buildings23 MW

What it could mean for IndiaWho builds RESCO solar in Punjab and J&K, and how fast

If you judge Punjab's solar market by the home rooftops going up, you see about 7 MW a month. One tender could add 50 MW through a few developers, on government buildings that the home counter does not count.

Few small installers may bid. Under RESCO the developer pays for the plants and earns that back over 25 years. Even the smallest bid, 1 MW, could mean Rs 10 lakh in earnest money: the tender charges Rs 10 lakh a MW, and its bid form lists the capacity bid beside the earnest money paid. A 1 MW winner then gives a Rs 20 lakh guarantee and pays Rs 13.5 lakh plus GST in service charges, project by project. In PEDA's June tender, a winner could, with its consent, have its earnest money counted as its guarantee. This tender has no such clause: a winner gets its earnest money back only after it signs and gives the guarantee, so it needs both in hand at once. That could favour developers with money in hand, though the small enterprise exemption in the tender's checklist could help some bidders.

The winners could still lean on local firms. A developer with sites across Punjab has to survey them, install, get meters connected and run the plants for 25 years, and some of that work could go to local crews, dealers who hold stock near the sites, and service teams. In J&K, where work orders are out, the review asked JAKEDA and the power utilities to get smart meters and power purchase agreements done alongside the plants, so that finished plants are not left waiting: the slow part of a RESCO plan may come after the work orders.

The headline size may matter less than what gets built. PEDA also asked for bids on 50 MW under RESCO in October 2023, Saur Energy reported at the time, and we could not find what came of that tender. This time, the tender makes bidders find the buildings, and PEDA takes no responsibility if a building is not available or does not sign. How much is awarded after 3 November, and how fast buildings sign, could say more about Punjab's market than the 50 MW itself.

What it means for youCrews, stock and panel rules for PEDA's RESCO tender

If you are an installer or dealer in Punjab: find out who bids and who wins; the techno-commercial bids are opened on 3 November. The tender says any change goes only on the state e-procurement portal, with no separate notice, so check it for corrigenda and pre-bid clarifications before 29 October. A winner with sites across Punjab could need survey teams, installers, stock close to the sites, help with meters and grid connection, which the tender puts wholly on the bidder, and service for 25 years. Offer that to bidders in writing, with your commissioning record.

If you plan to bid or to supply a bidder: the tender asks for DCR panels only, made in India and qualifying under the ALMM Order and the lists under it. It does not name List-I or List-II. MNRE's memorandum of 4 August 2026 says projects won in bids that close after 31 August 2025 are not exempt from List-II, the approved list of cell makers. Bids for this tender close on 29 October 2026, so on the memorandum's wording, price DCR panels with List-II cells. Our DCR story explains why cells made in India are short. Bidders should also ask PEDA for the draft power purchase agreement, which is not attached to the file we downloaded.

If you work in J&K: JAKEDA has work orders for 5,185 government buildings. If you have crews and stock in the UT, ask JAKEDA which firms hold those work orders, and offer those firms your crews and stock.

If you run a private factory, school or hospital: RESCO gets you solar without paying for the plant up front; instead you agree to buy its power for years. This tender is for government buildings only, but a private site can sign a RESCO deal with a developer directly. Before you sign, read the rate per unit and whether it goes up each year, how long the deal runs, how much power you must buy and who owns the plant at the end.

If you are a homeowner: this tender is for government buildings, and does not change how you apply under the national scheme or for the central subsidy.

Sources

  1. Government of Punjab, eProcurement System, Tender PEDA/2026-27/18 (Tender ID 2026_PEDA_176894_1): tentative 50 MWp grid-connected rooftop solar PV under RESCO mode in Punjab, with payment security mechanism. Tenders by Organisation, Punjab Energy Development Agency (read 14 Oct 2026), .
  2. PEDA, RFP Tender No. PEDA/2026-27/18 (eproc.punjab.gov.in, Tender ID 2026_PEDA_176894_1): tentative 50 MWp of grid-connected rooftop or ground-mounted solar under RESCO mode on government buildings in Punjab, with payment security mechanism. The 62-page document was downloaded from the portal (read 15 Oct 2026), .
  3. SolarQuarter, PEDA Invites Bids For 50 MW Grid-Connected Rooftop And Ground-Mounted Solar Projects In Punjab, .
  4. Mercom India, Punjab Energy Development Agency Floats Tender for Solar Projects, .
  5. Saur Energy, Punjab Floats 50 MWp Rooftop Solar Tender Under RESCO Model, .
  6. Mercom India, Punjab Energy Development Agency Invites Bids for 10 MW Solar Projects, .
  7. Punjab Energy Development Agency (PEDA), Tender No. PEDA/2026-27/08: e-bidding document, rate contract for about 10 MW of rooftop and ground-mounted solar on government buildings in Punjab and Chandigarh, .
  8. Saur Energy, Punjab Energy Development Agency Issues Tender for 50 MW Solar Projects, .
  9. Government of NCT of Delhi, Delhi Solar Portal, RESCO Model (read 14 Oct 2026), .
  10. Kashmir Observer, J&K Crosses 55% Rooftop Solar Target, 46,133 Homes Covered, .
  11. The Kashmir Images, J&K achieves 55% rooftop solar target under PM Surya Ghar scheme, .
  12. Ministry of New and Renewable Energy (MNRE), Office Memorandum No. 283/54/2026-GRID SOLAR: ALMM List-II for solar PV cells, clarification, .
  13. MNRE, National Portal for Rooftop Solar, PM Surya Ghar national portal, read daily by Solentra since 29 Aug 2026, .

The Solar Brief puts public reports in our own words and reads them against Solentra's own daily record of the PM Surya Ghar national portal. Where we say what something could mean, that is our reading, not a forecast. Nothing here is financial, loan or legal advice.

More from the Solar Brief

All Solar Brief stories

Want the numbers for your district, or a quote that is ready for a battery later?

Message us on WhatsApp.