PM Surya Ghar in Karnataka: rooftop solar progress
Karnataka has 26,022 rooftop solar systems installed under PM Surya Ghar: Muft Bijli Yojana, from 58,804 applications, as recorded on the Government of India national portal. That is No. 17 of India's 36 states and UTs.
Key figures
PM Surya Ghar in Karnataka, cumulative, as recorded on the national portal. The bar is Karnataka's share of India's total.
- Applications
- 58,8040.7% of India
- Installations
- 26,0220.5% of India
- Households covered
- 39,3520.7% of India
- Installed capacity
- 107.9 MW0.6% of India
- Subsidy released
- ₹183 Cr0.6% of India
Karnataka against India
How Karnataka compares with India
KarnatakaIndiaRank position
"Applications built" is installations as a share of applications, cumulative. Installations count systems; households count homes covered, and the two differ.
Only what is true for Karnataka
What stands out
- About 4 in 10 applications have become installations, against 6 in 10 nationally.
- Bengaluru Urban accounts for 37% of Karnataka's installations.
- The average system is 4.15 kW, larger than the national 3.51 kW.
Running total, one reading a morning
Installations, day by day
Karnataka recorded 434 new installations in the 7 days to 28 Sep, and 1,550 in September so far.
Running totalDaily changeLast 7 days
Every reading since 29 Aug
| Date | Applications | Installations | Change |
|---|---|---|---|
| 28 Sep | 58,804 | 26,022 | +10 |
| 27 Sep | 58,764 | 26,012 | +40 |
| 26 Sep | 58,690 | 25,972 | +68 |
| 25 Sep | 58,605 | 25,904 | +76 |
| 24 Sep | 58,507 | 25,828 | +71 |
| 23 Sep | 58,415 | 25,757 | +93 |
| 22 Sep | 58,317 | 25,664 | +76 |
| 21 Sep | 58,229 | 25,588 | +4 |
| 20 Sep | 58,203 | 25,584 | +63 |
| 19 Sep | 58,125 | 25,521 | +72 |
| 18 Sep | 58,032 | 25,449 | +73 |
| 17 Sep | 57,930 | 25,376 | +69 |
| 16 Sep | 57,853 | 25,307 | +51 |
| 15 Sep | 57,774 | 25,256 | +3 |
| 14 Sep | 57,758 | 25,253 | +3 |
| 13 Sep | 57,734 | 25,250 | +47 |
| 12 Sep | 57,646 | 25,203 | +77 |
| 11 Sep | 57,569 | 25,126 | +76 |
| 10 Sep | 57,489 | 25,050 | +82 |
| 9 Sep | 57,387 | 24,968 | +75 |
| 8 Sep | 57,279 | 24,893 | +47 |
| 7 Sep | 57,191 | 24,846 | +9 |
| 6 Sep | 57,175 | 24,837 | +52 |
| 5 Sep | 57,116 | 24,785 | +82 |
| 4 Sep | 57,026 | 24,703 | +78 |
| 3 Sep | 56,941 | 24,625 | +89 |
| 2 Sep | 56,855 | 24,536 | +149 |
| 31 Aug | 56,687 | 24,387 | +4 |
| 30 Aug | 56,664 | 24,383 | +38 |
One reading a morning. No reading was taken on 1 Sep; the change recorded after a gap covers the whole gap.
All 36 states and UTs, by installations
Where Karnataka ranks
Bar heights use a log scale, so the smallest states and UTs stay visible. Each step up the scale is ten times more installations.
| # | State / UT | Installations | Built |
|---|---|---|---|
| 15 | Jammu and Kashmir | 45,422 | 51% |
| 16 | Bihar | 31,689 | 12% |
| 17 | Karnataka | 26,022 | 44% |
| 18 | Punjab | 20,028 | 70% |
| 19 | Himachal Pradesh | 14,222 | 72% |
No. 17 of 36
Karnataka by installations recorded, among India's 36 states and UTs. By applications it is No. 19.
31 of 31 districts with applications
District-wise PM Surya Ghar progress in Karnataka
Bengaluru Urban has the most installations, with 9,548.
InstallationsAdded in the last 7 days
| District | Installations | Applications | Built | Capacity | Avg system | Subsidy | 7 days |
|---|---|---|---|---|---|---|---|
| 1Bengaluru Urban | 9,548 | 18,992 | 50% | 45.2 MW | 4.74 kW | ₹71.7 Cr | +196 |
| 2Dakshina Kannada | 3,130 | 3,904 | 80% | 12.2 MW | 3.90 kW | ₹21.8 Cr | +47 |
| 3Mysuru | 2,126 | 3,110 | 68% | 8.2 MW | 3.85 kW | ₹14.4 Cr | +33 |
| 4Udupi | 1,938 | 2,441 | 79% | 7.4 MW | 3.83 kW | ₹13.3 Cr | +30 |
| 5Belagavi | 1,265 | 2,149 | 59% | 4.4 MW | 3.49 kW | ₹8.27 Cr | +16 |
| 6Dharwad | 842 | 1,098 | 77% | 3.4 MW | 4.04 kW | ₹5.75 Cr | +4 |
| 7Shivamogga | 819 | 1,325 | 62% | 3.3 MW | 4.03 kW | ₹5.70 Cr | +7 |
| 8Uttara Kannada | 704 | 1,054 | 67% | 2.3 MW | 3.32 kW | ₹4.97 Cr | +7 |
| 9Bengaluru Rural | 625 | 3,277 | 19% | 2.5 MW | 4.01 kW | ₹4.10 Cr | +16 |
| 10Bagalkote | 545 | 951 | 57% | 2.0 MW | 3.66 kW | ₹3.79 Cr | +5 |
| 11Tumakuru | 419 | 1,912 | 22% | 1.6 MW | 3.74 kW | ₹2.63 Cr | +9 |
| 12Davangere | 393 | 2,444 | 16% | 1.4 MW | 3.60 kW | ₹2.43 Cr | +10 |
| 13Kalaburagi | 340 | 702 | 48% | 1.4 MW | 4.12 kW | ₹2.22 Cr | +5 |
| 14Ballari | 329 | 852 | 39% | 1.3 MW | 4.02 kW | ₹2.16 Cr | +3 |
| 15Vijayapura | 321 | 833 | 39% | 1.3 MW | 4.05 kW | ₹2.18 Cr | +2 |
| 16Hassan | 284 | 668 | 43% | 1.1 MW | 3.74 kW | ₹1.76 Cr | +2 |
| 17Raichur | 272 | 613 | 44% | 1.1 MW | 3.88 kW | ₹1.82 Cr | +4 |
| 18Mandya | 232 | 973 | 24% | 850 kW | 3.66 kW | ₹1.47 Cr | +1 |
| 19Chikkamagaluru | 227 | 1,098 | 21% | 828 kW | 3.65 kW | ₹1.46 Cr | +9 |
| 20Kodagu | 227 | 317 | 72% | 866 kW | 3.81 kW | ₹1.54 Cr | +4 |
| 21Chitradurga | 210 | 1,746 | 12% | 727 kW | 3.46 kW | ₹1.34 Cr | +2 |
| 22Vijayanagara | 192 | 339 | 57% | 737 kW | 3.84 kW | ₹1.23 Cr | 0 |
| 23Gadag | 176 | 319 | 55% | 618 kW | 3.51 kW | ₹1.12 Cr | +4 |
| 24Haveri | 166 | 533 | 31% | 581 kW | 3.50 kW | ₹1.13 Cr | +1 |
| 25Koppal | 165 | 497 | 33% | 636 kW | 3.85 kW | ₹1.05 Cr | +3 |
| 26Bidar | 130 | 400 | 33% | 490 kW | 3.77 kW | ₹80.2 L | +5 |
| 27Kolar | 127 | 2,089 | 6% | 447 kW | 3.52 kW | ₹78.2 L | +1 |
| 28Chamarajanagar | 88 | 164 | 54% | 318 kW | 3.61 kW | ₹56.1 L | +1 |
| 29Chikkaballapura | 79 | 3,252 | 2% | 313 kW | 3.96 kW | ₹47.2 L | +5 |
| 30Ramanagara | 76 | 607 | 13% | 297 kW | 3.91 kW | ₹43.7 L | +2 |
| 31Yadgir | 27 | 145 | 19% | 106 kW | 3.93 kW | ₹17.0 L | 0 |
All 31 districts are in the table: scroll inside it to see them.
6 DISCOMs handle net metering
By electricity distribution company
| DISCOM | Installations | Applications | Capacity |
|---|---|---|---|
| Bangalore Electricity Supply Company Ltd. (BESCOM) | 11,478 | 34,346 | 52.5 MW |
| Mangalore Electricity Supply Company Limited | 6,113 | 8,765 | 23.7 MW |
| Hubli Electricity Supply Company Ltd. (HESCOM) | 4,013 | 6,887 | 14.6 MW |
| Chamundeshwari Electricity Supply Company Ltd. (CHESCOM), | 2,957 | 5,219 | 11.3 MW |
| Gulbarga Electricity Supply Company Ltd. (GESCOM) | 1,455 | 3,541 | 5.8 MW |
| HRECS Hukeri | 6 | 46 | 20 kW |
-
Maharashtra
8,19,543
installations · No. 3
- Built
- 53%
- Avg system
- 3.66 kW
-
Goa
3,852
installations · No. 25
- Built
- 78%
- Avg system
- 8.23 kW
-
Kerala
3,60,722
installations · No. 5
- Built
- 76%
- Avg system
- 3.87 kW
-
Tamil Nadu
1,00,057
installations · No. 13
- Built
- 84%
- Avg system
- 3.66 kW
-
Andhra Pradesh
4,14,419
installations · No. 4
- Built
- 42%
- Avg system
- 2.82 kW
-
Telangana
65,916
installations · No. 14
- Built
- 69%
- Avg system
- 3.67 kW
Central subsidy
PM Surya Ghar subsidy in Karnataka
Karnataka receives the standard central subsidy: ₹30,000 per kW for the first 2 kW and ₹18,000 for the third, up to ₹78,000 for a system of 3 kW or more, paid into the household's bank account. How the subsidy and application work.
About these figures
Read automatically every morning from the PM Surya Ghar: Muft Bijli Yojana national portal (pmsuryaghar.gov.in, Ministry of New and Renewable Energy), with a daily record kept since 29 Aug 2026. Compiled by Solentra Energies, Mohali. Solentra is not affiliated with MNRE. See every state, district and DISCOM on the India rooftop solar tracker.